Gateway 5 Authority to Start Work: Southampton Buildings (40-45 Chancery Lane) - EE074

Report of the Director of the Built Environment.

Minutes:

The Sub Committee considered a report of the Director of the Built Environment regarding Southampton Buildings (40-45 Chancery Lane).

 

RESOLVED – That,

a)    a revised implementation budget of £221,305, as set out in section 5 of the report be approved;

b)    the use of £56,291 from the 40-45 Chancery Lane Section 106 Transport Improvements contribution, and £25,425 from the underspend of the Rolls Building S106 LCEIW contribution be approved;

c)    the detailed design as set out in section 1 and Appendix 3 of the report be approved;

d)    the progression of the project to implementation, in line with the programme as set out in section 3 of the report be approved.