The Sub-Committee considered a report of the Director of the Built Environment which provided a progress update on the Ludgate Hill Crossing.
RESOLVED – That the Sub-Committee:
a) approves the retention of the signalised crossing; and
b) authorises the utilisation of the remaining Works and Contingency budget of £34,340 to contribute towards the cost resurfacing of the carriageway in the vicinity of the crossing, as recommended by the Stage 3 Road Safety Audit.