Implementation of new Service Based Review Contract Management interventions - progress report

Report of the Chamberlain.

Minutes:

The Sub-Committee received a report of the Chamberlain updating on the implementation of the Service Based Review recommendations approved at the Efficiency and Performance Sub-Committee in March 2016.

 

The Sub-Committee was advised that the implementation of the SBR contract management recommendations was progressing in line with the plan to launch the service in April 2017.  Members of the newly established commercial unit had started joining the Corporation and a framework and supporting toolkit was in draft format and projected to be finalised by the end of February 2017.  Overall the status of the implementation was green with the only challenge being able to secure an Assistant Director to run the service, a role which might not be recruited to in advance of the April go live date.

 

RESOLVED – That the report be noted.

 