Report of the City Surveyor.
Minutes:
The Committee considered a report of the City Surveyor setting out the Outline Options Appraisal relative to the Tower Bridge HV System Replacement and Increasing Electrical Resilience.
RESOLVED – That the Planning and Transportation Committee:
1. Approve recommended Option B;
2. Approve a budget of £303,000 to reach the next Gateway;
3. Note the revised project budget at £5.8m (excluding risk);
4. Note the Costed Risk Provision in the total sum of £2,600,000;
5. Note the revised project timeline changes from GW 1-2.